PINE NEEDLE LNG COMPANY, LLC
Critical: N
Notice Eff Date: 02/07/2014
Notice Eff Time: 10:02:09 CST
Notice End Date: 02/28/2015
Notice End Time: 00:00:00 CST
Notice ID: 5585806
Notice Stat Desc: Initiate
Notice Type Desc: Other / Waste Heat
Post Date: 02/07/2014
Post Time: 10:02:09 CST
Prior Notice: 0
Reqrd Rsp Desc: No response required
Rsp Date:
Rsp Time:
TSP: 013081810
TSP Name: PINE NEEDLE LNG COMPANY, LLC

Notice Text:

Subject: Waste Energy Recovery Opportunities for Interstate Pipellines

INGAA issued a study dated February 2008 and a follow up report on November 2009 on the referenced subject. Williams is participating in this initiative on a voluntary basis with Pine Needle LNG Company, LLC (Pine Needle).

 

To meet the INGAA requirements, a turbine engine must have an ISO rating of 15,000 horsepower (or greater) with run times of at least 5,250 hours per year (60% load factor) during the calendar year 2013.

 

Pine Needle does not have any gas turbine engines; therefore, Pine Needle does not have any equipment that meets the INGAA requirements.

 

 Please direct any questions to Bob McChane (713) 215-3630.